Page 1. 9/18/07 item 4.
the plan..and it’s foundation.
more logix blocks (about $20/each ).. on 10/5/7..
bracing for the wall pour..
10/14 grading and preparation for the last pour..
Framing starts 10/17/7
10/19 Subflooring.
10/22 what a beautiful day for wall ing…